How Do I... Correct Schedule Errors
There are three types of schedule errors:
You can see a list of all schedule errors by printing the Job Schedule Errors report.
To correct No Resource, or Conflict schedule errors, follow these steps:
| Open Job |
| Select a Job in the drop down list at the top of the main window. |
| Print Schedule Errors |
| Click on Schedule in the shortcut menu, then click on Print Schedule Errors to view and print a list of job schedule errors. |
| Open Schedule Entry |
| Click on Schedule in the shortcut menu, then click on Edit Schedule to open the Edit Schedule form. |
| Right-Click Flagged Cell |
| To correct schedule errors, right-click on the schedule cell for the item and date with the error. This will display the Resource Schedule Update form. The Resource Schedule Update form displays a description of the schedule conflict in the "Conflict" box, and allows you to change the date and/or the Resource scheduled for that item. |
| Click OK |
| Once you have completed making changes to the resource schedule information, Click OK. This will save your changes, and re-display the Job Schedule form. |
If you corrected a No Resource error, the "nr" flags should be cleared on all the schedule dates for the item you clicked.
If you corrected a Conflict error, the "C" flag should be cleared on the date for the item you clicked.
To correct Cost Not Scheduled errors, follow these
steps:
| Open Job |
| Select a Job in the drop-down list at the top of the main window. |
| Click "Job" |
| Click on the Job button, then click on Estimate to go to the Job Edit Job Estimate form. |
| Select Job Item |
| Locate and click on the item in the list on the left side of the screen. This will display the item information in the right side of the screen. |
| Check Schedule Box |
| Click on the Schedule box. |
| Click OK |
| Click OK to save changes. |