Edit Job Estimate Form
To open the Edit Job Estimate form, click on Job in the shortcut menu, then click Edit Job Estimate. Or, click Estimate at the bottom of the Edit Job form.
A job estimate is defined by any number of job items. You use the Edit Job Estimate form to add or edit job items.
Important: Please read How Do I... Structure Job Items? for information on how to break down an estimate into job items.
The Edit Job Estimate form consists of the job item selection box on the left side of the screen, and a "tabbed" box with prompts for job item information and job site photos on the right side of the screen.
The tabbed box has the following tabs.
The item selection box is discussed here.
| Item Selection Box |
The item selection box is on the left side of the Edit Job Estimate form. It allows you to...
Right click in the item selection box to see a popup menu with these, and other options.
To use the item selection box:
| Select An Item: |
|
To select an item, click on the item in the list box on the left side of the form. You can also select job items by pressing the arrow keys to move the highlight to the desired item. When an item in the item selection box is selected, it becomes highlighted, and information about that item appears in the prompts on the right side of the screen (see below). |
| To Add A New Item: |
| Click Add (or type Alt-A). Fill in the prompts on the right side of the screen. Then Click OK at the bottom of the screen. The new item will appear in the list directly below the previously selected item. |
| To Add A New Sub-Item: |
| Click Sub-Item (or type Alt-S). The program will create a copy of the current item, indented beneath it. Change or add to the prompts on the right side of the screen. Then Click OK. |
| To Copy an item from this job: |
|
| To Copy an item from another job: |
| Position the highlight where you want to copy the item. Click Copy From... (or type Alt-F). This will display the Copy From tab. Select a job, click on an item, then click Copy. The item will be inserted into the list at the position of the highlight. You can reposition the highlight and select other items to copy any number of times. |
| To "Split" An Item: |
|
Highlight the item to be split and click Split (or type Alt-T). This will create multiple sub items under the current item. A separate sub item will be created for each "job section" that you have selected in the prompt for Job Sections: in the Edit Job form. See How Do I... Use Job Sections for more information. Note: You cannot split an item if any of the following conditions are true:
|
| To Delete An Item: |
| Highlight the item to be deleted and click Delete. |
Note: You cannot delete an item if any of the following conditions are true:
| To expand a group item: |
To expand a group item (make all of the sub-items visible), you can:
|
| To expand all items: |
| Click Expand (or Alt-E) to display all of the items in all of the groups in the list box. Click Shrink (or Alt-H) to hide all of the items in all of the groups in the list box. |
Note: The expanded state of all items in the list will be restored the next time you enter the job Edit Job Estimate form. The same expanded state of the item list is also restored in the Job Progress entry form. The Job Progress entry form can re-arrange the expanded state of items in the list, but it is not saved, so it does not affect the expanded state stored by the Job Estimate Information entry form.
| To move items: |
| You can arrange the items in the list box in any order, and in any grouping, as follows. |
You can move items using the arrow buttons to the right of the list box:
| To save changes: |
| Click OK, or select another item. Changes are automatically saved when you select another item. |
| To cancel changes: |
| Click Cancel. |
| To print a job listing: |
|
Click Print. This will display a popup menu to allow you to print the job three ways:
|
| To exit the form: |
| Click Cancel (if any changes were made), then click Exit to close the job estimate form. |
| To view Estimate Grid form: |
| Click Estimate Grid to go to the Job Estimate Grid entry form. |
| To go back to Job Information: |
| Click Back to go back to the Edit Job form. |
| Item Info tab |
The job Item Info tab has the following prompts:
| Item Name: |
| Enter the name of the item. This will appear in the list of items to the left, as well as in all reports that list job items. |
| Job Phase: |
|
Select an Job Phase from the drop-down list. You can select from the pre-defined list of Job Phases, or you can create your own Job Phase by typing it and pressing the [Enter] key, or by clicking Add. Click Edit to edit the Job Phase. Click "=" to set sub-items to the same Job Phase. The Job Phase is used for a number of purposes:
|
| Vendor/Sub: |
|
Vendor where the item will be purchased, or the name of the subcontractor if the item will be subcontracted. Select a Vendor/Subcontractor from the list, or type a new one and press [Enter], or click Add to create a new Vendor/Subcontractor. Click Edit to edit the Vendor/Subcontractor. Click "=" to set sub-items to the same Vendor/Subcontractor. The Vendor/Sub prompt associates a vendor or subcontractor with an item so that Smart Contractor can automatically create Purchase Orders, and enter Purchases. Note: The Vendor/Sub prompt will be disabled if the current item has been purchase ordered or purchased. To change the Vendor/Sub, remove the item from the purchase order in the Purchase Order entry form, and/or the purchase transaction in the Purchase entry form. |
| Product: |
|
This is the name of the specific product to be purchased. Select from the list, or type the name and press [Enter] to create a new Product. The name should be detailed
and descriptive enough to identify the product for purchasing, including the make, model, and dimensions if applicable.
Note: Products can be listed by Job Phase. To list only products for the job phase selected above. Click the toggle button to the right of the prompt so that it shows a "-". To view all products, click again, so that it shows a "+". You assign products Job Phase in the Enter Product form. The Product prompt assigns a product to the estimate item. The program will automatically retrieve product prices entered in the Enter Product form the first time you edit an estimate item. After the first time you edit the estimate item, you must click the "$" button to retrieve product prices from the product database. Note: The Product prompt will be disabled if the current item has been purchase ordered. To change the Product, remove the item from the purchase order in the Purchase Order Entry form. Note: The prompt for Count Unit (below) will be disabled when a product is selected. For quote requesting and other purposes, the estimate must use the same unit as what is set in the product information. |
| Description: |
|
Enter descriptive information about the product being purchased for this particular job item, such as size, color, etc. For example, if you are purchasing two different colors of ceramic tile that are otherwise the same, you can create a single product for the tile, and assign that product to two different job items, but just entere the different color in the Product Description field of each job item. The product description is printed with products in purchase orders. |
| Lead Time: |
|
Enter the item Order Lead Time in Days. This is the number of days that an item must be ordered in advance of when it will be delivered. |
| Item Count: |
| Enter the estimated item count.
Note: Use the Job Progress entry form to update this item with the actual count used. |
| Calc (Count Calculator) |
| The Count Calculator button (Calc) appears to the right of the prompt for Item Count. Click the Count Calculator button to display the Count Calculator form. The Count Calculator is used to calculate the count of products to be purchased for a job item. See the Count Calculator topic for information. |
| Count Unit: |
|
Select the item count unit. You can select from the pre-defined list of count units, or you can create a new count unit by typing it and pressing the [Enter] key. Note: The prompt for Count Unit will be disabled when a product is selected in the prompt for Product (above). For quote requesting and other purposes, the estimate must use the same unit as what is set in the product information. |
| Percent Waste: |
|
Enter a percentage of waste to be added to the estimated count of materials. The program will automatically calculate the total materials to purchase based on the estimated count (Item Count), and the percent waste. |
| Materials/Unit: |
|
Enter the item material cost per unit. This is the contractor's cost - before adding the item markup. The Materials cost per unit prompt is followed by a display of the total cost of materials based on the Item Count and the Materials cost per unit entered. Note: Use the Job Progress entry form, or the Purchase entry form to enter actual material costs. See How Do I... Track Job Costs for information on how to enter estimated and actual item costs. |
| Subcontract: |
|
Enter the item subcontract cost per unit. This is the contractor's cost - before adding the item markup. The Subcontract cost per unit prompt prompt is followed by a display of the total subcontract cost based on the Item Count and the Subcontract cost per unit entered. Note: Use the Job Progress entry form, or the Purchase entry form to enter actual subcontract costs. See How Do I... Track Job Costs for information on how to enter estimated and actual item costs. |
| Equipment: |
|
Enter the estimated total equipment cost for this item. See How Do I... Track Job Costs for information on when and why to enter equipment costs separately. |
| Other: |
|
Enter the estimated total other cost for this item.. See How Do I... Track Job Costs for information on when and why to enter "other" costs separately. |
| Total Cost: |
| Displays the total cost for the current item, calculated as sum of (Materials /Unit x Item Count) + Equipment + Subcontract + Other + Total Labor. |
| Customer Price: |
| Displays the total customer price for the current item, calculated as Total Cost plus markups and sales tax (if applicable). You can set an item as taxable by checking the Taxable box in the Miscellaneous tab. |
| Hours Per Unit or Dollars Per Unit |
|
Enter the estimated labor hours per item count unit. For example: if the item is "Siding", with an item count = 2000, and count unit = "Square Feet", then if you enter 0.10 Labor Hours /SqFt, the program will automatically calculate a total of 200 hours labor for the 2000 square feet of siding. See additional notes about Labor Costing below. |
| "hr/u" or "$/u" Button |
|
This button switches the previous Hours Per Unit / Dollars Per Unit prompt back and forth between entering labor costs in Hours Per Unit, or Dollars Per Unit. The prompt indicates whether costs are entered as hours or dollars: If the labor cost per unit prompt says Hours Per Unit, enter labor costs as hours per unit, or click this button to change to Dollars Per Unit. If the labor cost per unit prompt says Dollars Per Unit, enter labor costs as dollars per unit, or click this button to change to Hours Per Unit. When you enter labor costs in Dollars Per Unit, Total Labor is calculated as Dollars Per Unit x Item Count, and Total Hrs is calculated as 1 / (Labor Rate / Total Labor). When you enter labor costs in Hours Per Unit, Total Hrs is calculated as Hours Per Unit x Item Count, and Total Labor is calculated as (Total Hrs / Labor Rate). Note: When you enter labor costs as Dollars Per Unit, if you do not enter the labor rate (or select any employee recources from the Resources prompt), the program will set the labor rate to the total labor cost, and set the hours to 1. When you enter a labor rate (or select (an) employee recource(s) from the Resources prompt), the program will calculate the hours. Use the Employee entry form to set the labor rates for employee resources so that these will be automatically used when you select the employee from the Resources prompt. The Schedule Item box below must be checked in order to select employees from the Resources prompt. |
| Labor Rate: /Hour |
|
Enter the estimated labor cost per hour. If the work will be performed by more than one employee, you can enter the total cost per hour for all employees, or you can let the program calculate that automatically. To do that, you must:
When you do, the prompt for Labor Rate will display the total estimated labor cost (per hour) for all of the employees that you select in the prompt for Resource below. |
| Total Hrs: |
|
Displays the total labor hours calculated as the Labor Hours /Unit times the item Count Unit. Note: If Labor Hours/Unit is zero, you can enter the total hours and the program will calculate the Labor Hours/Unit (hours per count unit) as Total Hrs divided by Item Count. |
| Total Labor: |
|
Displays the total labor cost calculated as Labor Rate * Total Hours. |
| Allowance: |
| Check if the item is an allowance item. Allowance Items appear in the Allowance Schedule. |
| Punch List Item: |
| Check if the item is a punch list item. Punch list items appear in the Punch List report. |
| Schedule Item: |
|
Check the Schedule Item box to add the item to the job schedule. See How Do I... Schedule A Job? for more information. |
| Days (Duration): |
|
The estimated number of days to schedule work for this item. Days Duration defaults to the duration defined in the schedule model for the job if you do not enter estimated labor hours. If you enter estimated labor hours, then Days Duration is automatically calculated as Total Hours (displayed above) divided by the number of employees selected in the Resource prompt (below) times Schedule Work Hours Per Day (entered in the Job Options form). |
| Schedule Phase: |
|
Enter the job phase (number) that this item belongs to. For example, if you indicate in the prompt for Job Phases in the Edit Job form, that the job will have 2 phases, enter 1 for phase 1, or 2 for phase 2. Note: If the item is a group item (has sub items), all sub items will be assigned to the same phase. See How Do I... Schedule A Job In Phases? topic for more information. |
| Resource: |
|
When you click on the Resource prompt, a box will open containing the list of Resource(s) that can be scheduled to work on the job item. Check the box next to a resource in the list to assign them to the job item. You can assign any number of resources to a job item. Resource Notes: The Respource prompt will be disabled (greyed out) until you check the Schedule Item check box. As you click on resources to assign them to the job item, you will notice that the number in the prompt for Labor Rate above will be updated (unless you have selected an entry in the prompt for Labor Cost Rate - see below). That number is the sum of the hourly Labor Cost Rates that have been assigned to the resources in the Resource entry form. For example: say you assign two employees to a job item, Joe and Marty. Joe has been set up (in the Resource entry form) with Labor Cost Rate = "Skilled Labor", and Marty as been set up with Labor Cost Rate = "Foreman". If "Skilled Labor" is defined (in the Cost Rate entry form) with a Cost Rate of $20.00, and "Foreman" is defined with a Cost Rate of $40.00, then the Labor Rate for the job item will be $60.00 after you assign both Joe and Marty to the job item. Also, as you click on resources to assign them to the job item, you will notice that the number in Days Duration will be updated. Days Duration is calculated as Total Hours (displayed above) divided by the number of employees selected in the Resource prompt times Schedule Work Hours Per Day (entered in the Job Options form). The Resource prompt will be disabled if the Schedule Item check box (above) is not checked. You have to schedule an item in order to assign resources to it. Click the Add button to the right, or use the Resource entry form, to add to the list of Resources. Don't worry about accidentally assigning a resource to more than one job on the same day. The job schedule will display a "C" (for Conflict) on days on which a resource has been scheduled for more than one job. Right click on that schedule day to view information about the schedule conflict and to change the resource(s) assigned to that item. |
| Item Note: |
| Enter any notes pertaining to this item to be printed on the customer's job listing and invoice. The prompt for these notes appear here, and in the Edit Job Estimate form. The prompt for this note appears here, and in the Job Progress entry form. |
| Spell Check Button |
| Click the "abc check" button to spell check the Item Notes. |
| Miscellaneous Tab |
|
The Miscellaneous tab contains the following prompts: |
| Materials Markup: |
|
Enter the markup percent of item material costs. You can set the material cost markup separately for each item. Note: Use the prompt for Markup Calculation Method in the Job Options setup form to determine whether the markup is calculated as a percent of the job cost ("markup"), or as a percent of the job price ("margin"). |
| Labor Markup: |
|
Enter the markup percent of item labor costs. You can set the labor cost markup separately for each item. Note: Use the prompt for Markup Calculation Method in the Job Options setup form to determine whether the markup is calculated as a percent of the job cost ("markup"), or as a percent of the job price ("margin"). |
| Equipment Markup: |
|
Enter the markup percent of item equipment costs. You can set the equipment cost markup separately for each item. Note: Use the prompt for Markup Calculation Method in the Job Options setup form to determine whether the markup is calculated as a percent of the job cost ("markup"), or as a percent of the job price ("margin"). |
| Subcontract Markup: |
|
Enter the markup percent of item subcontract costs. You can set the subcontract cost markup separately for each item. Note: Use the prompt for Markup Calculation Method in the Job Options setup form to determine whether the markup is calculated as a percent of the job cost ("markup"), or as a percent of the job price ("margin"). |
| Other Charge Markup: |
|
Enter the markup percent of item other costs. You can set the other cost markup separately for each item. Note: Use the prompt for Markup Calculation Method in the Job Options setup form to determine whether the markup is calculated as a percent of the job cost ("markup"), or as a percent of the job price ("margin"). |
| Taxable: |
|
This prompt is not visible unless a Retail Sales Tax percent OR a Cost Sales Tax percent is entered in the Edit Job form. The Taxable check box is used to indicate whether the job item is taxable (under sales taxes). By default, the Taxable
check box is checked when you add a new item. If the item is not taxable, click on it to un-check it. |
| Purchase Wholesale: |
|
This prompt is not visible unless a Retail Sales Tax percent AND a Cost Sales Tax percent is entered in the Edit Job form. The Purchase Wholesale check box is used to indicate whether the job item is purchased wholesale. By default, the
Purchase Wholesale check box is set to the setting of the Purchase Wholesale check box for the product selected. If no product
is selected, the Purchase Wholesale check box is not checked by default. Items with the Purchase Wholesale check box unchecked will not have a sales tax line item added to customer invoices, but the program will automatically add the Cost Sales Tax percent to the estimated material cost. |
| Completion Req: % |
|
Note: This option only applies to the Hourly Labor Schedule. Enter the percent by which an item must be completed in order to be scheduled to start at any point after the start of the day. Examples:
|
| Prevailing Wage Rate: |
|
Disabled unless Prevailing Wage Job option is checked in the Edit Job form. Select a prevailing wage rate (from the defined list of Labor Cost Rates) to be used to override the individual labor cost rates for employees assigned to the job item (in the Resource prompt in the Item Info tab). The Prevailing Wage Rate is used to calculate the labor rate per hour for a prevailing wage job. The Prevailing Wage Rate selected for the job item supercedes the labor cost rates assigned to employees (in the Employee Entry form). See How Do I... Use Prevailing Wage Rates? for more information. |
| Job Section: |
|
Select a job section to assign this item to. The drop down list includes all of the job sections that you have checked in the prompt for Job Sections: in the Edit Job form. Note: The drop down list will be empty if you have not checked any sections in the prompt for Job Sections: in the Edit Job form. See the How Do I Use... Job Sections? topic for more information. |
| Print Options And Alternatives: |
| Click this button to print a listing of the options and alternatives in this job. |
| Optional Item: |
| Check Optional Item if the item is an optional item. Optional items allow you to provide customers with a different estimate for the job with the optional item(s) added. See How Do I... Use Options And Alternatives for more information. |
| Option Name: |
| Enter or select a name for the optional item. Optional items with the same name are totalled under that option name in the job listing. See the How Do I... Use Options And Alternatives topic for more information. |
| Alternative Item: |
| Check Alternative if the item is an alternative to another item in the job. Alternatives allow you to provide customers with a different estimate for the job with the alternative item(s) used instead. See How Do I... Use Options And Alternatives for more information. |
| Alternative Name: |
| Enter or select a name for the alternative. Alternative items with the same name are totalled under that alternative name in the job listing. See the How Do I... Use Options And Alternatives topic for more information. |
| Print Change Orders: |
| Click this button to print a listing of the change orders in this job. |
| C.O. Cancel: |
| Check C.O. Cancel and enter a name in the prompt for C/O to add this item to a Change Order. |
| Change Order: |
| Enter the change order name to associate cancelled items with a change order. |
| C.O. Add: |
| Check C.O. Add and enter a name in the prompt for C/O to add this item to a Change Order. |
| Change Order: |
| Enter the change order name to associate added items with a change order. |
| Journal Note: |
| The Journal Note prompt allows you to enter journal notes for your internal use. These notes will not be printed on any customer correspondence or documentation. The prompt for these notes appear here, and in the Job Progress entry form. These notes are also printed on the Job Journal Notes report. |
| Spell Check Button |
| Click the "abc check" button to spell check the Journale Notes. |
| Job Site Photos Tab |
The Job Site Photos tab allows you to store digital photos for the currently selected job item. To store a photo in Smart Contractor, the photo must already be downloaded from the camera to a diskette, CD, your computer's hard drive, or a drive that is available on your network.
In other words, to store a photo in Smart Contractor, first use the software that came with your camera to download the photo to your hard drive. Then follow the steps below to store photos in Smart Contractor.
To Add a photo, follow these steps:
| Select the job item |
| Photos are stored separately by job item. To store or view photos, select a job item. To select a job item, highlight the item in the item list box. |
| Click on the Job Site Photos tab |
| Display the photo entry form by clicking on the Job Site Photos tab. |
| Click Add Photo |
| Click the Add Photo button. This will display a "Select Job Site Photos" browse dialog box that will allow you to locate and select a photo to add. Select the photo, and click Open. |
| Enter a caption |
| When you add a photo, the program will add the photo to the Job Site Photos tab with a caption that says "Enter Caption Here". Click on this text to select it. Then type a caption for the photo. |
Repeat this process for as many photos as you need for the current job item. Then click OK (below the Add Photo button) to save changes.
Note: You can store any number of photos in each job item, but since it takes about 1/2 a second to load a photo of typical size, the lag becomes significant when you store more than 6 photos for a particular item.
To remove a photo, click on the photo to remove, then click Remove. This will remove the photo from Smart Contractor. It will not remove or delete the photo from the folder where you originally copied it into Smart Contractor.
To print the photos for the job, click Print on the Job Site Photos tab. This will display the Job Site Photos listing. You can print a merge document for customer use with the Job Site Photos Document. When the photos are printed, they are arranged (sorted) according to item scheduled date, job item, and photo date.
| Copy From Tab |
The Copy From tab appears when you click the Copy From button (or when you click on the Copy From tab).
The Copy From tab allows you to add items to a job by copying them from other jobs, or from the job template.
The job template comes with the Smart Contractor. It contains various examples of jobs and job items. You can add items to your job by copying them from the job template, or from any other job.
When a job item is copied, it is inserted at the point where the highlight is positioned in the item selection box (to the left of the screen). You can insert a single job item, or a group item (that contains any number of sub-items)
To copy job items into the job you are working on:
| Position Item Selection Highlight |
| Position the item selection highlight in the item selection box (at the left of the screen) at the point where you want to insert the job item(s). You can move the highlight with the arrow keys or the mouse. |
| Click Copy From |
| Click the Copy From button. This will display the Copy Item tab in the right half of the screen. |
| Select a job |
| In the Copy Item tab, select a job in the drop-down list at the "Job To Copy From:" prompt. This will display the job items in the box below. |
| Select item to copy |
| Select the item that you want to copy. If you select a "group" item (that has a "+" next to it or items under it), this will copy the item and all sub-items into your job. |
| Click Copy |
|
This will copy the selected item(s) into your job at the position of the highlight. You can select and copy any number of job items into your job at any time. Be sure to position the highlight in your job each time before you copy an item. |
| Job Total Tab |
The Job Total tab appears when you click on the Job Total tab.
The Job Total tab displays following totals for the current job:
|
|
| Links Tab |
|
The Links Tab contains a grid to allow you to store links to external documents that are associated with the current job. The Links grid has the following columns: |
|
|
| Description |
|
Enter a description of the external document file. |
| Link |
|
Displays the path to the external document file. Click on the "..." button to either browse to, or open the link. Important: Files must be located in a "network share folder" in order to be accessible from all computers on a network! Please consult your network administrator for assistance with setting up network share folders. |
| Status |
|
(Optional) Select a status to assign to this external document. |
| Notes |
|
Enter any notes for this external document. |
| Customer Web |
|
Check this box to indicate that this document should be made available on the customer's information website that is created by Smart Contractor. See the "Setup Website Publishing" topic for more information. |
| Vendor Web |
|
Check this box to indicate that this document should be made available on the Vendor/Sub's information website that is created by Smart Contractor. See the "Setup Website Publishing" topic for more information.
|
Copyright © 2004-08 Smart Construction Software, LLC; All Rights Reserved